We have begun the secure run. Because we made bigger overhangs which will be enclosed we changed the run adding 12 more feet and eliminating another proposed more open run. A lot of time was spent measuring and spacing the post holes. We put 4x4 every 12' and anchored in concrete. The we built 36" on center 2x4 posts and lifted them into place. Overhead we used 2x4's and joist hangers to nail the roof panels to.






























Half the run has wire and under galvanized panel roofing.





2/3 under metal roof, 1/3 clear plastic



It's actually very nice inside the run now. The dust bath is at the end with clear panel roofing.
Hope the Chickens like it!